25 minutes ago
(This post was last modified: 24 minutes ago by C C.)
RELATED (scivillage): US facing extreme power transmission crisis, experts warn
- - - - - - - - - - - -
Transformer shortages loom for strained US power grid
https://www.eurekalert.org/news-releases/1151533
INTRO: As growth in artificial intelligence forces the United States to expand its power supply, a new study finds the country will soon hit a surprising roadblock: shortages of key materials needed to connect new data centers and power plants to the grid.
In a first-of-its-kind study, Johns Hopkins University researchers found the country could run short of critical grid supporting equipment, such as transformers and converters, as early as next year, with acute shortages hitting by 2030.
“This type of equipment was taken for granted but without it, you can build a data center or a power plant but it won’t be powered because you cannot connect it to the grid,” said author Yury Dvorkin, a researcher with expertise in modeling power and infrastructure demand. “When the demand for electricity started to grow faster than expected, it started to amplify all the cracks in the industry.”
The work published today in Cell Reports Sustainability. Historically the country’s power demand has grown incrementally, at a percent or two a year. But thanks to power-hungry data centers, growth in electric vehicles, and other needs, power use is projected to grow 21% by 2030.
The ability to grow the U.S. power grid and to refurbish aging infrastructure depends on the availability of key equipment, including, most importantly, power transformers and transformers for data centers. There are also things like charging equipment for electric vehicles, and power electronics converters for wind power, batteries and solar panels.
The materials needed to build transformers and other grid-supporting equipment include copper, steel, nickel, aluminum and manganese. The U.S. is in danger of running out of all of them over the next four years, the Johns Hopkins study found.
Dvorkin and Boyu Yao, a PhD candidate in Civil and Systems Engineering who studies the challenges for evolving power grids, modeled power demand projections alongside global supply chain data to determine whether the country would have the materials needed to support data center growth in coming years. The study is the first to precisely quantify expected shortages by equipment type and material.
The team projects the U.S. will run short of copper next year, effecting not only equipment for data centers, but also converters for wind power generation and electric vehicle charging infrastructure.
Steel and nickel will be nearly impossible to source by 2030, the team found. Under baseline scenarios, or modest growth in power demand, by 2030 the nation would likely have enough transformers, but fall about 16% short of other grid-supporting equipment.
But if high power demand continues as expected, over the next four years the researchers project the U.S. will be almost 15% short on transformers and 30% short on other critical equipment. As much as two-thirds of all the expected equipment shortages will be fueled by data centers, according to the researchers... (MORE - no ads)
- - - - - - - - - - - -
Transformer shortages loom for strained US power grid
https://www.eurekalert.org/news-releases/1151533
INTRO: As growth in artificial intelligence forces the United States to expand its power supply, a new study finds the country will soon hit a surprising roadblock: shortages of key materials needed to connect new data centers and power plants to the grid.
In a first-of-its-kind study, Johns Hopkins University researchers found the country could run short of critical grid supporting equipment, such as transformers and converters, as early as next year, with acute shortages hitting by 2030.
“This type of equipment was taken for granted but without it, you can build a data center or a power plant but it won’t be powered because you cannot connect it to the grid,” said author Yury Dvorkin, a researcher with expertise in modeling power and infrastructure demand. “When the demand for electricity started to grow faster than expected, it started to amplify all the cracks in the industry.”
The work published today in Cell Reports Sustainability. Historically the country’s power demand has grown incrementally, at a percent or two a year. But thanks to power-hungry data centers, growth in electric vehicles, and other needs, power use is projected to grow 21% by 2030.
The ability to grow the U.S. power grid and to refurbish aging infrastructure depends on the availability of key equipment, including, most importantly, power transformers and transformers for data centers. There are also things like charging equipment for electric vehicles, and power electronics converters for wind power, batteries and solar panels.
The materials needed to build transformers and other grid-supporting equipment include copper, steel, nickel, aluminum and manganese. The U.S. is in danger of running out of all of them over the next four years, the Johns Hopkins study found.
Dvorkin and Boyu Yao, a PhD candidate in Civil and Systems Engineering who studies the challenges for evolving power grids, modeled power demand projections alongside global supply chain data to determine whether the country would have the materials needed to support data center growth in coming years. The study is the first to precisely quantify expected shortages by equipment type and material.
The team projects the U.S. will run short of copper next year, effecting not only equipment for data centers, but also converters for wind power generation and electric vehicle charging infrastructure.
Steel and nickel will be nearly impossible to source by 2030, the team found. Under baseline scenarios, or modest growth in power demand, by 2030 the nation would likely have enough transformers, but fall about 16% short of other grid-supporting equipment.
But if high power demand continues as expected, over the next four years the researchers project the U.S. will be almost 15% short on transformers and 30% short on other critical equipment. As much as two-thirds of all the expected equipment shortages will be fueled by data centers, according to the researchers... (MORE - no ads)